2011 Sewer Lining Project Affected Streets
The City of Urbana is upgrading 11,000 feet of sewer pipe to maintain the integrity of the sanitary sewer system in the area. Beginning Tuesday September 6, 2011 through Tuesday September 27, 2011 weather permitting Hoerr Construction from Peoria, Illinois will be performing sewer lining at various locations around Urbana.
You will be notified via a door hanger brochure if the sanitary or storm sewer that serves your house is being lined. This sewer lining process relies on trenchless sewer reconstruction technology that does not involve time consuming, expensive and disruptive open excavations. Instead of digging up and replacing the old pipe, the cured-in-place process provides for the insertion of a special lining inside the old pipe. The new liner creates a watertight, smooth-surfaced and long-lasting pipe within the old sewer.
Streets affected by the Sewer Lining Project include:
- Anderson Street –Mumford Drive to Brighton Drive
- Beardsley Avenue – Romine Street to Goodwin Avenue
- Briarcliff Drive - Cottage Grove Avenue to Philo Road
- Cottage Grove Avenue – Michigan Avenue to Pennsylvania Avenue
- Cottage Grove Avenue – Mitchem Drive to Mumford Drive
- Curtiss Drive – Florida Avenue to Vermont Avenue
- Florida Avenue – Anderson Street to Grove Street
- Laurel Drive – Philo Road to Michigan Avenue
- Maple Street – University Avenue to Main Street
- Matthews Avenue - Beardsley Avenue to Bradley Avenue
- Michigan Avenue – Cottage Grove Avenue to Philo Road
- Mumford Drive – Cottage Grove to Fletcher Street
- Mumford Drive – Anderson Street to Lynn Street
- Oregon Street – McCullough Street to Cedar Street
- Penn Court
- Pennsylvania Avenue – Wiley Drive to Philo Road
- Poplar Street – Main Street to Green Street
- Rainbow Court
- Rainbow View – Weaver Street to Hunter Street
- Romine Street – Beardsley Avenue to Bradley Avenue
- Rutledge Drive – Florida Avenue to Vermont Avenue
- Silver Street – Anderson Street to Silver Court
- East Silver Court
- East Springfield Avenue – Goodwin Avenue to Matthews
- Vermont Avenue – Lincoln Avenue to Orchard Street
One or more lanes of a street may be closed at the lining locations to accommodate the Contractor’s equipment and set-up. Generally, lining is completed within one day at the location so any traffic impacts will be temporary. We apologize for any inconvenience this may cause. Concerns or questions may be directed to Mr. Brad Bennett at (217) 384-2316.