UCSD Sewer Lining Project Lane Closures

Date: 
February 1, 2012 - 7:30am - 7:30pm

As part of the Urbana Champaign Sanitary District’s Annual Sanitary Interceptor Maintenance Project, the District’s Contractor, KIM Construction, will be lining the manholes that run north along Vine Street starting on Wednesday, February 1st at 7:30 A.M. and ending on Wednesday February 1st at 7:30 P.M. weather permitting.

Traffic will be affected on the following streets during the cleaning and lining work:

  • Vine Street from Fairlawn Drive to Oregon Street

One or more lanes of a street may be closed at these locations to accommodate the Contractor’s equipment and set-up. We apologize for any inconvenience this may cause.

Javascript is required to view this map.
Map Locations: 
Contact Reference: