Boneyard Creek Improvements Project Construction Update
Between rain events, the north abutment wall was poured and the deck beams were placed for the Race Street Bridge. The contractor also completed driving the sheet piles and soldier piles required for Perimeter Wall #2, the retaining wall just east of the building at 208 Griggs Street.
Elsewhere on the project site, streetscape work continued along Broadway Avenue between Water Street and University Avenue. Streetscape work included pavement removals, storm sewer modifications, curb, gutter and sidewalk replacement, and brick placement along the back of the curbs. The open areas between the brick edge and sidewalk will be landscaped in the Fall or Spring.
In June 2013, construction efforts will remain focused on completing the new Race Street Bridge, repairing deteriorating timbers on the railroad trestle bridge and constructing the retaining walls adjacent to the bridge. Streetscape work will continue on Broadway Avenue and begin on Race Street in the vicinity of the Race Street Bridge.
![]() | ![]() | ![]() |
If you are interested in seeing a few more pictures, please visit our Flickr page by clicking here.
E-mail Updates: If you are interested in receiving e-mail notifications regarding construction progress and street closures associated with the project, please send an e-mail to Brad Bennett at bmbennett@urbanaillinois.us and you will be added to the notification list.
Thank you in advance for your patience and cooperation during construction of the Boneyard Improvements Project.
| Type | File | Size |
|---|---|---|
| Project Update - June 2013 | 624KB | |
| Project Update - May 2013 | 633KB | |
| Project Update - April 2013 | 600KB | |
| Project Update - March 2013 | 1.2MB | |
| Project Update - February 2013 | 307KB | |
| Project Update - January 2013 | 319KB | |
| Project Update - December 2012 | 712KB | |
| Construction Schedule | 280KB | |
| Construction Phasing Plan | 821KB |