HOT TOPICS

Lincoln and Springfield Resurfacing Project

Project Status: 
Pending
Estimated Completion: 
Jul 2022
Estimated Cost: 
$0

Project Location:  Lincoln Avenue from north of Green Street to south of University Avenue and Springfield Avenue from east of Gregory Street to west of Coler Avenue.

Project Activities: Includes hot-mix asphalt surface removal and replacement, pavement patching, curb and gutter
removal and replacement, sidewalk repair, and other miscellaneous work.

Project Updates: These will be done as steps in the project process move along.

Project Questions: please contact projects@urbanaillinois.us