HOT TOPICS

Lincoln and Springfield Resurfacing Project

Project Status: 
In Progress
Estimated Completion: 
Jul 2022
Estimated Cost: 
$2,300,000

Project Location:  Lincoln Avenue from north of Green Street to south of University Avenue and Springfield Avenue from east of Gregory Street to west of Coler Avenue.

Project Activities: Includes hot-mix asphalt surface removal and replacement, pavement patching, curb and gutter
removal and replacement, sidewalk repair, and other miscellaneous work.

Project Updates: These will be done as steps in the project progresses

  • August 30, 2021: initial installation of project signage and start of lane closure information for the southboud (right/western) lane of Lincoln Avenue from Clark Street to Springfield Avenue
  • September 1, 2021: initial lane closure starts for the southbound side of Lincoln Avenue (right/western lane) from Clark Street to Sringfield Avenue
  • September 7. 2021: temporary no parking restrictions on West Clark and West Main (both west of Lincoln Avenue)

Project Questions: please contact projects@urbanaillinois.us