Construction & Staging Information - 2018 Full Depth Concrete Patching Project - Part 1

Bid Results:  Bids were opened May 16, 2018.

Contractor:  The lowe bidder was Feutz Contractors, Inc., 1120 N. Main St., Paris, IL 61944

Current Status:  Construction is expected to start Friday, July 27, 2018.

% Complete:  0% as of July 27, 2018.

Staging Sequence:

Two-way traffic will be maintained at all times with a minimum of one-lane two-way traffic.

Driveways will be out of service on an "as-needed" basis for a maximum of 1 day.

 