Project Status:
Complete
Estimated Completion:
Nov 2020
Estimated Cost:
$4,325,000
Project Limits:
Green Street from Busey Avenue to Race Street
Project Description:
Transformation of Green Street to a complete street within the project limits.
For Pedestrians:
- Clearly defined street crossings supplemented with pavement markings and signs
- New American with Disabilities Act (ADA) compliant sidewalks and curb ramps
- Pedestrian drop-off points
For Bicyclists:
- New bicycle lanes on either side of Green Street
For Transit Users:
- New bus shelters
- New information kiosk
For All Users Including Motorists:
- Completely new concrete pavement between Busey Avenue and Race Street
- Improved street and sidewalk drainage via storm sewer modifications
- Recessed pavement markings and improved traffic control signage
- New landscaping (trees and plantings)
Other Improvements:
- New sanitary sewer between Busey Avenue and McCullough Street
- New water main from Busey Avenue to Race Street
MCORE Project 5 Updates:
https://www.urbanaillinois.us/mcorep5updates
MCORE Projects 1 through 5
For more information about MCORE Projects 1, 2, 3, 4 and 5, please visit mcoreproject.com.